Financing: ICRC
Partner: GFA
Project timeline: June 2020 – February 2021
The goal of the Assignment is to perform a detailed assessment of the current financial, economic, operational and organizational performance of Voda Donbassa in order to provide the utility with a strategic direction and guidance to become a technically and financially stable and sustainable organization.
The objectives of the technical and operational audit are:
- Present the legal framework under which Voda Donbassa operates
- Audit the regulatory reporting forms completed by Voda Donbassa
- Operational assessment of Voda Donbassa
- Establish suitable indicators to assess the capacity and performance of the Company
- Benchmark the performance of the Company
- Understand present the operational and strategic challenges faced by Voda Donbassa
- Propose Strategic actions and direction
The purpose of the objectives is to promote sustained delivery of water and wastewater services